Schedule a Project Task or Sub Task
- Open a Project and click on the Tasks tab. A list of Tasks and Sub Tasks will open
- Put the form in EDIT mode and edit the Start Date and Time of a Task directly in the grid. The End Date and Time will adjust automatically based on the listed Duration
- Alternatively, Tasks and Sub Tasks may be scheduled using the Project form Extended Menu. Highlight one or more grid lines, and from the Extended Menu select ‘Change Selected Start Dates,’ ‘Change Selected End Dates,’ or ‘Shift Dates for Selected’
- Alternatively, Users may drill into an individual Task or Sub Task and make Start or End Date edits there
- Finally, Start and End Dates may be changed using the Project > Extended Menu > Gantt Chart. Place the chart in EDIT mode and then click and drag Tasks and Sub Tasks to desired positions. Dependent (linked) Tasks and Sub Tasks will move with each other
- Note: Target Effort and / or Scheduled Effort may be similarly edited using any of the above methods